Integrated Cassava Processing Infrastructure. A modular, specification-grade native starch facility in Edo State, Nigeria, designed to be the reference asset for LisBonFARM's agro-industrial portfolio.

Design basis

Engineered for consistency at industrial scale.

Uniform lines simplify procurement, spares and operator training, and allow capacity to be added without redesign. Each line is sized to the feedstock the catchment can reliably deliver.

Fresh-root input
1,200 TPD design capacity, with 12.5–15% engineering margin
Configuration
Three uniform 400 TPD lines, commissioned in sequence
Annual root demand
~396,000 tonnes at nameplate, 330 operating days
Native starch output
~90,000 tonnes per year at design basis
Packaging
25 kg, 50 kg and jumbo bags for industrial buyers
Energy
Gas-based base load, grid backup, biogas from process effluent
Water
Process water treatment and effluent treatment to discharge standard

Phasing

Capacity added in step with proven performance.

Line 1 is commissioned and stabilised first. Lines 2 and 3 follow together once operating milestones are met, completing the 1,200 TPD Phase 1 facility. Phase 2 is planned as adjacent capacity with modified starch.

01,200 TPD Phase 11,800 TPD

Phase 1A

Line 1 · +400 TPD

First line commissioned and stabilised

Phase 1B

Lines 2 + 3 · +800 TPD

Added together once Line 1 milestones are met

Phase 2

Expansion · +600 TPD

Planned: modified starch and adjacent capacity

Phase 2 remains subject to engineering, funding, land, market, permitting, governance and execution completion.

Product

Food-grade native starch to a published specification.

Specification-grade output is what separates an industrial supplier from a commodity processor. Every lot is released by the in-house laboratory against the target specification.

Target product specification
ParameterTarget
Whiteness≥ 95%
Moisture≤ 13%
Ash≤ 0.15%
Fibre≤ 0.10%
Specks≤ 2 / cm²
Fineness≥ 99.8% through 100 mesh
pH5.5 – 7.0
OdourNeutral

Value ladder

One feedstock base. A path to higher-value products.

Stage 1

Native starch

Food-grade native cassava starch. The Phase 1 product and the foundation of the investment case.

Stage 2 · Phase 2

Modified starch

Planned Phase 2 derivative line serving food and industrial applications with higher value per tonne.

Stage 3 · Planned

Sweeteners

Glucose syrup, dextrose and fructose (F55) from starch hydrolysis, on the same feedstock and utility base.

Stage 4 · Planned

Sorbitol

The highest-value polyol in the ladder, produced from glucose for pharmaceutical, oral-care and food markets.

Site and land

A candidate site has been identified in Edo State, within Nigeria’s southern cassava belt. Engagement with the landholding community is under way.

In line with standard project-finance practice, land rights will be documented as a registered long-term lease held by the project company, with Governor’s consent, as a condition to financial close. Land engagement is structured to align with IFC Performance Standards 1 and 5: willing parties, fair compensation and no involuntary displacement.

Feedstock architecture

The supply model is diversified by design, so no single channel determines plant utilisation. Suppliers are tiered by committed monthly volume and scheduled to a 24–48 hour harvest-to-process window.

Outgrower networksAggregatorsNucleus estate

Target architecture. Supply agreements are being developed ahead of financial close.

Conceptual rendering of the root intake gate, weighbridge and delivery lanes
Conceptual rendering of root reception and yard operations
Conceptual aerial rendering of the processing complex and logistics yard

Conceptual renderings of the planned facility.

Development status

The path to financial close.

  1. May 2025

    Project company incorporated

    LISBONFARM LTD registered in Nigeria (RC 8508608) as sponsor and developer.

    Complete
  2. Jun 2026

    Design basis defined

    1,200 TPD fresh-root platform, three uniform 400 TPD lines, food-grade native starch target specification.

    Complete
  3. 2026

    OEM proposals received

    Preliminary technical and commercial proposals from established starch-line equipment manufacturers.

    Complete
  4. Aug 2026

    Integrated financial model

    Phase 1 and planned Phase 2 investment case, with base, lender and downside scenarios.

    Complete
  5. —

    Site and community engagement

    Candidate site in Edo State; engagement with landholding community under way.

    In progress
  6. —

    Feedstock supply network

    Engagement with outgrower networks and aggregators across the supply catchment.

    In progress
  7. —

    Primary equity raise

    Up to US$20 million, through a controlled process with qualified investors.

    In progress
  8. —

    ESIA, permits and FEED

    Environmental and social assessment to IFC Performance Standards; front-end engineering design.

    To financial close
  9. —

    Contracts and land lease

    EPC contract, feedstock and offtake agreements, registered long-term land lease.

    To financial close
  10. —

    Senior debt and financial close

    Project-level debt from development finance and commercial lenders.

    To financial close